Open Audit Recommendations

Below is a list of our open audit recommendations. When a report is issued, the Postal Service responds to each recommendation, and if there is agreement, it provides a corrective action plan with a date of planned implementation. We request written confirmation from the Postal Service when those corrective actions are completed and evaluate this information and provide concurrence when the recommendation can be closed. 
 
If the Postal Service disagrees with a recommendation, we work towards agreement by elevating discussions between USPS and OIG management.  Any recommendations that the Postal Service does not act on remain open and are reported to Congress until a resolution is achieved.

 
158
 
$197,075,164
Report Title Report Number Issue Date Report Open Recommendations
Image
USPS Loyalty Program Cover
The Path Forward for the Postal Service Loyalty Program 23-072-R23 3
# Recommendation Value Status Initial Management Response Final Resolution
1

Establish performance targets aligned with the key objectives of a new loyalty program and establish parameters to actively monitor progress for effective program management.

$0 Open Agree
2

Develop a comprehensive communication strategy for a new loyalty program that promotes awareness of functionality for prospective, and once enrolled, ongoing customers.

$0 Open Agree
3

Conduct an evaluation of customer spending requirements and discounts, related to any future loyalty program, to ensure the program's design promotes customer engagement and shipping growth

$0 Open Agree
Image
23-035 Cover
Progress Made to Reduce Mail Excluded from Service Measurement 23-035-R23 2
# Recommendation Value Status Initial Management Response Final Resolution
1

Explore and evaluate options to incentivize mailers to resolve mail exclusions.

$0 Open Agree
2

Communicate and provide training to Full-Service mailers on the online portal and exclusion tool, and on how to identify root causes and resolve mail exclusions.

$0 Closed Agree
3

Develop and implement a strategy to track, identify, and record Service Performance Measurement defect codes and root causes.

$0 Open Disagree
4

Evaluate the feasibility of providing exclusion information at the mailpiece level to enable mailers to reduce Service Performance Measurement exclusions.

$0 Closed Agree
Image
SDC Q1 Q2 Cover
Review of USPS Sorting and Delivery Centers in FY23 Q1 and Q2 23-062-R23 2
# Recommendation Value Status Initial Management Response Final Resolution
1

Develop and implement policy to ensure all future Sorting and Delivery Center plans are consistently and clearly communicated and stakeholders are given the opportunity to report concerns.

$0 Closed Agree
2

Develop a plan to ensure restroom, breakroom and locker room construction projects are completed prior to opening Sorting and Delivery Centers, or that there are acceptable alternatives, given the number of employees impacted, and that the alternatives meet all health and safety requirements.

$0 Closed Agree
3

Evaluate whether construction projects related to the seven facilities were completed and develop a plan to address all outstanding construction and safety issues.

$0 Open Agree
4

Identify the cause of late Post Office Box up-times and take necessary action to ensure up-times are met. Additionally, develop a plan to mitigate issues with Post Office Box up-times prior to opening future S&DCs.

$0 Open Agree
5

Require documentation be maintained to verify sort programs are updated, loaded, and tested prior to opening new Sorting and Delivery Centers.

$0 Closed Agree
Image
Return on Investment Capital Projects Cover
Return on Investment for Capital Projects 23-036-R23 2
# Recommendation Value Status Initial Management Response Final Resolution
1

Extend the tracking and compliance reporting period for capital projects, based on asset type and dollar amount, to better assess the project's success.

$0 Open Agree
2

Develop a centralized repository enabling management to access pertinent project documentation for effective tracking and reporting.

$0 Open Agree
Image
Efficiency PnDC New Orleans Cover
Efficiency of Operations at the New Orleans Processing and Distribution Center, New Orleans, LA 23-112-R23 2
# Recommendation Value Status Initial Management Response Final Resolution
1

Document Priority Mail Express delays in the Mail Arrival Quality/Plant Arrival Quality system and coordinate with the Louisiana District Manager to resolve the Priority Mail Express issues.

$0 Open Agree
2

Develop and implement a process to verify delayed mail count procedures are followed.

$0 Closed Agree
3

Coordinate with plant management to train clerks and supervisors at the New Orleans Processing and Distribution Center on proper mail flow procedures in processing operations and verify these procedures are followed.

$0 Closed Agree
4

Initiate the corrective action process with contractors not meeting their delivery schedules, as required by the Postal Operations Manual.

$0 Closed Agree
5

Coordinate to develop and implement a plan to verify load scanning at the New Orleans Processing and Distribution Center is consistently completed in accordance with policy.

$0 Open Agree
6

Verify all drivers are using wheel chocks at the New Orleans Processing and Distribution Center.

$0 Closed Agree
Image
Postal Service Use of Automated Guided Vehicles Cover
Postal Service’s Use of Automated Guided Vehicles 23-057-R23 2
# Recommendation Value Status Initial Management Response Final Resolution
1

Develop and execute a plan to evaluate Automated Guided Vehicle locations, and require and monitor usage to improve performance.

$28,832,154 Open Agree
2

Train and share best practices and usage goals with personnel at processing facilities that will have Automated Guided Vehicles to improve performance.

$0 Open Agree
3

Direct responsible personnel to confirm the accuracy of Automated Guided Vehicle capital asset listings and update information in the Solution for Enterprise Asset Management system and maintenance system records.

$0 Closed Agree
Image
Repair_Maint_PkgSortMachines_DR_Cover_AP
Repair and Maintenance of Package Sorting Machines at Delivery Units 23-089-R23 1
# Recommendation Value Status Initial Management Response Final Resolution
1

Instruct the Philadelphia P&DC to
perform and confirm completion of all required preventive maintenance on a consistent basis on the ADUS at Paschall Station

$0 Closed Agree
2

Provide ongoing informal training for
SDUS clerks by a subject matter expert or on-the-job trainer at the unit, where the trainer can instruct personnel in the
proper procedures for daily preventive maintenance for the SDUS.

$0 Open Agree
3

widely distribute - to include delivery units with package sorting equipment - a policy on the proper usage of emergency stop buttons.

$0 Closed Agree
4

Develop a plan to provide the delivery units visited with the resources needed to effectively run their operations, and in the interim, develop a plan to best use the resources on hand, taking into account optimal start times for machines based on employee availability and mail volume.

$0 Closed Agree
5

Require anyone assigned to operate package sorting machines within delivery units to receive training on the proper operation of that machine - including start up and shut down procedures and inducting mail onto the machine.

$0 Closed Agree
6

Complete the ongoing project to effectively track and document changes, including the deployment of new equipment across the Postal Service network, to ensure that all machines are entered into eMARS timely.

$0 Closed Agree
7

Consider directing local management at the four delivery units visited to develop and maintain a method of communication between operations and maintenance personnel to improve transfer of knowledge of identified issues and solutions.

$0 Closed Agree
8

Instruct local management at the four delivery units visited to improve communication - to include the use of huddle boards - and oversight of package sorting machine performance to increase efficiency of the operation.

$0 Closed Agree
9

Periodically reinforce to personnel at the four delivery units visited the need to open a MTSC ticket with complete and accurate information of identified maintenance issues, when required.

$0 Closed Agree
Image
PRC Travel Expenses
Postal Regulatory Commission Travel Expenses 23-027-R23 3
# Recommendation Value Status Initial Management Response Final Resolution
1

Implement an electronic review and approval function within the existing digital repository of travel documents.

$0 Closed Agree
2

Conduct a cost-benefit analysis of either appointing personnel with full travel authority and oversight responsibility or allowing travelers to be responsible for submitting, tracking, and supporting their travel actions and expenses in eTravel.

$0 Open Agree
3

Update the travel policy to reflect the needs of the Postal Regulatory Commission and align with agency priorities.

$0 Open Agree
4

Create a training program about the travel process and require employees that travel to complete this training and retake as needed when changes to the process occur.

$0 Open Agree
Image
Surface Transfer Centers WestPac Cover
Efficiency of Surface Transfer Centers in the Western Pacific Region 23-031-R23 1
# Recommendation Value Status Initial Management Response Final Resolution
1

Implement weekly reviews of the Key Performance Indicators and assess penalties when performance targets are not met.

$281,973 Closed Agree
2

Add all contractual Key Performance Indicators to the Surface Transfer Center Report Card.

$0 Closed Agree
3

Require local Surface Transfer Center officials to submit Postal Service Form 6166 to the supplier and to Headquarters management for increased visibility and decision making when performance targets are not met.

$0 Open Agree
4

We recommend the Vice President, Transportation Strategy, in coordination with the Vice President, Logistics, include Key Performance Indicators in future Surface Transfer Center contracts that are renewed or awarded to suppliers.

$0 Closed Agree
Image
Cremated Remains Cover
Cremated Remains 23-018-R23 1
# Recommendation Value Status Initial Management Response Final Resolution
1

Develop and implement a process for reoccurring communication of Cremated Remains acceptance procedures to retail clerks nationwide.

$0 Closed Agree
2

Develop and implement guidance requiring retail clerks to verify Cremated Remains are prepared and packaged in accordance with Postal Service policy.

$0 Closed Agree
3

Update the Cremated Remains acceptance procedures requiring retail clerks to place Cremated Remains packages in individual Priority Mail Express sacks at acceptance.

$0 Open Agree
4

Reiterate the procedures for monitoring Cremated Remains and develop a process for validating that In-Plant personnel review the Informed Visibility report daily for delayed Cremated Remains packages in accordance with policy.

$0 Closed Agree
5

Evaluate the feasibility of requiring customers to use the Cremated Remains kit boxes when shipping Cremated Remains and revise policy as appropriate.

$0 Closed Agree
6

Develop a plan to ensure Cremated Remains kit boxes are readily available to customers.

$0 Closed Agree